Tough 'N' Easy Flooring - Installation Instructions

       Tough 'N' Easy Illustration

      Tough and Easy Installation Instructions

  1. Tough and Easy Tiles must be site conditioned at room temperature for 48 hours prior to installation. During this period, room temperature must be maintained at 70º F +/- 5º F (21º C +/- 3º C).

  2. Begin by calculating the exact center of the room.

  3. Start laying tiles from the center of the floor towards the walls. First lay the full tiles. Then proceed with the trimmed tiles around the walls.

  4. Tough and Easy Tiles can be easily cut with a sharp utility knife, a jigsaw or a circular saw.

  5. A space of approximately 1/4" (6mm) should be left as an expansion gap around the walls and any other obstacles, such as pillars.

  6. Under normal circumstances, the Tough and Easy Tiles do not require adhesives. But, it is recommended that they be cemented in place in the following situations:

    a. If the floor is exposed to high temperatures; i.e. in direct sunlight.

    b. If the tiles will have to resist extremely high dynamic pressure.

    c. If the tiles will be exposed to excessive liquids.

    d. If tiles are installed in cold temperature, i.e. under 70º F (21º C).

  7. In he even of there being heavy machinery, the tiles should be laid around the machines rather than under them and the expansion gap should be included as per number 5 above.

      Back to Tough and Easy Flooring Page

Tough 'N' Easy Flooring

        Adhesives are not required for most applications but are recommended when the floor will be subject to heavy and continuous moisture levels or if it will be exposed to direct sunlight. In such cases, when cementing in place is recommended, the substrate must be smooth, dry and dust free. Tough 'N' Easy Flooring has been extensively proven in demanding operational conditions in laboratory controlled tests covering chemical and electrical resistance, flammability, elasticity, indentations, heat aging and sound insulation.
       Maintenance: Tough 'N' Easy Flooring resist oil and chemical attack and are rot proof, however it is wise to remove any spillage as soon as possible. General maintenance such as sweeping, damp mopping, or the use of a cylindrical scrubber combined vacuum machine for dry washing are recommended. An emulsion dressing may be used.
       Please note: Single-sided or double-sided edging is available for interfacing the material with surrounding flooring or to provide a beveled and finished edge.
General Specifications
Architectural Specifications
Back to Tough and Easy Flooring Page
Back to Industrial Flooring Index Page
Site Map: The Mat King Web Site in Overview
 

THE MAT KING
740 West End Avenue; Suite 1
New York, NY 10025 USA

Phone: 646-998-4208
Fax: 646-998-4073
Phone: 800-442-6544
Fax: 800-Mats-Fax (628-7329)